Office move IT checklist

Order fibre, check cabling, plan the comms cupboard and phones, then test it all before move day.

Short answer

Start the IT side of an office move as soon as the lease is signed. Order the internet connection first, because installs can take weeks. Check the new site's data cabling, comms cupboard and Wi-Fi coverage, plan where desks and printers go, arrange phone number moves, and test everything before staff arrive.

Last updated 25 November 2026

Why it happens

The internet is ordered too late

A new fibre connection, or moving an existing one, often needs a site visit and an install booking, and that can take weeks. If the building has never had fibre to your floor, it can take longer. Offices that leave this until the last fortnight end up working off phones. Ordering early and having a 4G or 5G backup ready covers delays.

The new building's cabling is not what it seems

Wall ports that look fine may be old phone cabling, not network, may not be connected at the cupboard end, or may not reach where the desks will sit. A cable test before moving shows which ports work and at what speed. Adding or patching cabling is far easier in an empty office than around desks, staff and a deadline.

Small details stop the office on day one

The comms cupboard may have no ventilation or only one power point. Printers need new addresses, desk phones need their numbers moved, and Wi-Fi access points need placing for the new layout. Nobody wrote down router passwords or how the server is set up. Each is small, but together they turn the first morning into a long list of problems.

Try these first

  1. As soon as you have the new address, ask your internet provider for the earliest install date and whether fibre already reaches your floor.
  2. Get a floor plan and mark where each desk, printer, TV and Wi-Fi access point will sit, then compare that with the existing wall ports.
  3. Ask the landlord for any cabling records and check the comms cupboard has power points, ventilation and space for your rack or equipment.
  4. Contact your phone provider about moving numbers and desk phones, and confirm the date they will switch over.
  5. Make a list of every IT device to move, with passwords and settings written down, and check backups have run the week before.

When to stop. Stop before arranging power changes, new sockets or anything involving mains wiring in the new office. That work needs a registered electrician. Do not unplug and pack the server without a recent, tested backup. If the building has asbestos warnings in ceilings or walls, cabling work must wait until that is cleared by the right people.

Tried these and still stuck?A technician can sort it at your place or remotely. Free quote for bigger jobs.

What our technician does

We visit the new site to test existing cabling, check the comms cupboard and plan Wi-Fi coverage. We coordinate with your internet and phone providers, add or patch data cabling, and set up the router, switches and access points before move day. On the day we disconnect, move and reconnect computers, printers and the server, then test every desk. Office moves are project work, so you get a free written quote before anything starts. After-hours and weekend moves can be booked ahead.

Questions people ask

How far ahead should we start planning?

As early as you can, ideally as soon as the lease is signed. The internet install is usually the longest wait. Cabling, equipment orders and a site visit can follow. Leaving a few weeks of breathing room before move day avoids most of the last-minute problems.

Can we move over a weekend so work does not stop?

Yes. Many offices pack on Friday afternoon, move over the weekend and start fresh on Monday. That only works if the internet, cabling and network are tested at the new site beforehand, so plan the IT side to finish first.

Is a move a good time to upgrade equipment?

Often it is. Replacing an ageing router, switches or Wi-Fi during the move means one disruption instead of two. Old servers can be retired in favour of cloud storage. We can quote upgrades alongside the move so you can choose what is worth doing.

Get a technician on itSend the details now - photos help - and we'll reply with a time and the likely cost.

Similar problems

Call 09 243 1686Book a technician